Do you need an EPC?

In any construction project, your EPC company is your most important asset or your biggest liability. As your FOAK will be at least ten times bigger than your demo, don’t expect that your own team will be able to handle it better than a seasoned EPC contractor. The knowledge your team gained during the building of the demo will serve you well now when you will be selecting and negotiating with the EPC. A good EPC can breeze through a project. ATOME, a UK startup in green ammonia, secured an EPC contract with Casale S.A., a leader in ammonia technologies with over 100 years of experience.

It will be tempting to select someone who can offer you a better rate. Don’t go down that road. Aim instead for the best-of-class EPC. Hiring a reputable EPC contractor will add confidence for your investors. The best EPC contractors out there might be wary of doing an unfamiliar project, but they also might be willing to add a new type of project to their portfolio. You have to understand the EPC business model. The EPC business is tough. Your project pipeline horizon is usually no more than two years. You constantly juggle cashflows from several projects, and being asset-light makes it hard to get loans. So EPC’s survive by their reputations and portfolios. Adding a new, complex project like your FOAK, opens up a lot of future possibilities for an EPC. Keep this in mind during your negotiations.

Rosatom planned its first lithium-ion gigafactory in Kaliningrad, where construction start was planned for 2023. In 2025, the process has just started, while a new factory near Moscow, that was planned for only in 2022, has been nearing completion. The only difference was an EPC contractor. For the Kaliningrad factory an obscure EPC from Novosibirsk was selected, presumably because of its lucrative low price. For the Moscow factory, a local, highly reputable EPC was selected.

Hiring an EPC is like hiring an artist. You have to go and see its previous works, and talk with its previous clients. This will give you some insight into their customer relations and project management approach. Do your due diligence. You don’t want your EPC shutting down due to cash problems in the middle of your project. Finally, negotiate the price. A fixed-price full-wrap agreement with EPC would guarantee the total cost of the project.

Due to many unknowns of a FOAK, EPC will try hard to keep its options open and resist a fixed-price agreement. Negotiate around pass-through prices for items bought only if you are the one who will be doing the procurement of these items. Anything that is under EPC control should be its full responsibility. Exceptions can be made, but with extreme caution, and when there are no other options available.

Now, there are exceptions to this. The fastest completed construction project that I know was built without hiring an EPC, by a team that had not done this before. The JR Energy Solution 500 MWh electrode factory was built in just eight months, start to finish. Duke Oh, the founder and the CEO, explained to me that in his previous project, he planned for a gigafactory, but was not able to complete it. Now, he went through the same process, albeit at a smaller scale, and decided that an EPC will just get in his way.

EPC is called EPC for a reason. It pulls together and coordinates all of the aspects of a construction project. The real skill of an EPC is not in mastering some or all letters of its alphabet soup - engineering, procurement, or construction. It is in planning, coordinating, and managing these and other essential project parts, like finance, logistics, and even local politics. It is a leadership position, rather than a technical one.

When Duke was planning his factory, he decided that his and his team’s knowledge of the suppliers, engineers, and construction companies is good enough to take charge of EPC himself. It is necessary to keep in mind that this was not the first-of-its-kind electrode factory. The business concept of manufacturing-as-a-service was new in the battery industry, but not the manufacturing of electrodes itself. Can thus the experience of JR Energy Solution in going without an EPC contractor be applied to a true FOAK? Yes, and here is how.

As I was telling in the previous section, you will be hard-pressed to find an EPC for your demo, so it is highly likely that you will be managing all of the aspects of building a demo yourself. This will give you a perspective of what it is like to be an EPC. You will be able to develop, or hone your skills as an EPC. But that’s not all. To succeed without an EPC contractor, you need to know very well the companies that make up an EPC team - the engineering, the suppliers, and the construction company. Building a demo gives you a chance to develop these relationships.

If you managed your demo build-up fine and developed good working relationships with engineers, planners, suppliers, etc, you might be ready to try and do the EPC work yourself. Founders’ other duties, like fundraising, investor relations and what not, might prevent you from doing so. Or you might just no like the process and seek out a dedicated EPC. And sometimes, you would want an EPC, but won’t be able to find one that would agree to do your FOAK at your conditions. Exploring the option to be an EPC yourself doesn’t mean that you have to take the role. It’s just that - an option. You might choose to take it, or the circumstances might force you to. But at least, you’ll be ready.