Writing /

FOAK climate tech monthly, August 2026

August was all about green ammonia. One megaproject crossing the finish line and another one fighting for survival. In the background, Europe is shutting down battery resilience and localisation projects, while announcing economic support initiatives doomed to fail. Let's sort the signal from the noise.


The Good News

NEOM Green Hydrogen finally moved from the "Noise" section to "Good news" by announcing the completion of its $ 8.5 B green ammonia project this month at Oxagon — the world's largest commercial-scale facility of its kind. Commissioning is now underway with first operations targeted for 2027.

Despite all my doubts about NEOM, construction completion on a project this size is a genuine inflection point for green hydrogen. It will be the reference case for cost, schedule and offtake reality for all further green ammonia projects. But I have that feeling that NEOM is shrinking to just this project.

Form Energy closed a $750 million round to scale production of its iron-air batteries. This is serious capital for long-duration energy storage and suggests institutional investors see a path to deployment beyond the pilot in Minnesota. But I want to see that $20/kWh mark hit.

ATOME Villeta resurfaced with a partnership with a multilateral development bank to advance a 300 MWp solar project near Villeta — apparently trying to build its own power supply after the Paraguayan government pulled the rug on its PPA earlier this year. Nice to see ATOME doubling down on the project.

The Bad News

Lifthium Energy, the Portuguese FOAK of 8,000-ton lithium hydroxide plant in 2027, got scrapped this month, right after securing a €180M government grant. This demonstrates again that grants aren't enough if you want to build your own resilient battery supply chain. Without some sort market pull in a form of the end consumer subsidy, this won't work.

The Noise

Stegra (née H2 Green Steel) appeared on a list of startups to watch for IPO and in a market forecast projecting green steel to $200 billion by 2034. When you look at it through the prism of the latest news of failures to raise private capital, the IPO looks a bit desperate.

Kairos Power continues to build at Oak Ridge, with the Hermes reactor visibly taking shape since the April groundbreaking — but August's news was all about NuCAMP, a workforce training initiative with ORNL, and a partnership announcement with TVA and Google for future advanced nuclear in East Tennessee.


Three takeaways

  • NEOM green hydrogen reaching construction completion is the most significant green hydrogen milestone globally — now the entire sector watches commissioning and ramp-up for the real cost and performance data.
  • ATOME regrouping after a blow by the government of Paraguay cancelled its PPA with its own solar plant, shows that the project might still survive.
  • Lifthium demonstrating how not to do a localisation project.

Next month I'll be watching NEOM commissioning progress and whether Stegra has anything physical to report from Boden before winter.

All writing